Description of Figure 3

The graphic is of the Integrated Corridor Management Roadmap.
The Integrated Corridor Management Roadmap runs from the third
quarter of FY 2004 through the fourth quarter of FY 2011 and consists
of four phases plus two cross-cutting activities.
Initial Cross-Cutting Activity - Develop Program Plan and
Engage Stakeholder Working Group: six items
- Establish and Engage Multimodal Stakeholder Working Group:
Q1-FY2005 to Q4-FY2011
- Develop Draft Program Plan for Stakeholder Review: Q3-FY2004 to
Q1-FY2005
- Revise Program Plan: Q2-FY2005 to Q3-FY2005
- Update Program Plan: Q1-FY2006 to Q2-FY2006
- Update Program Plan as Necessary: Q2-FY2007 to Q1-FY2008 and
beyond
- ICM Support: Q2-FY2008 to Q4-FY2011
Phase 1: Foundational Research: nine items and one decision point
- Phase 1.1: Develop Generic ICM Concept: Q2-FY2005 to Q3-FY2006;
and
- Phase 1.1 continued: Update ICM Concept as Necessary: Q4-FY2006
to Q1-FY2008 and beyond
- Phase 1.2: Conduct ICM Foundation Research: Q2-FY2005 to Q2-FY2006
- Phase 1.3: Document Successful Local Integration Efforts:
Q2-FY2005 to Q2-FY2006
- Phase 1.4: Identify Corridor Types, Operational Approaches and
Strategies, and Analysis Tools: Q3-FY2005 to Q3-FY2006
- Phase 1.5: Determine ICM Development Feasibility: Q3-FY2005 to
Q3-FY2006
- Decision Point No. 1: Development Feasibility: Are there
sufficient integration issues and likelihood of success and benefits to
justify further work? Q4-FY2005
- Phase 1.6: Integrated Corridor Management Focus Groups: Q2-FY2006
to Q4-FY2006
- Phase 1.7: Provide Technical Assistance to ICM Stage 1 Pioneer
Sites: Q2-FY2006 to Q3-FY2006
- Phase 1.8: Transit Issues, Contributions, and Perspectives in ICM:
Q4-FY2006 to Q4-FY2007
Phase 2: Corridor Tools, Strategies, and Integration: two items
- Phase 2.1: ICM Tools and Strategies: Q2-FY2006 to Q4-FY2011
- Phase 2.2: Prototyping ICM System Components: Q1-FY2007 to
Q4-FY2010
Phase 3: Corridor Site Development, Analysis, and Demonstration: three
items, four milestones, and two decision points
- Milestone: Post Request for Applications (RFA): Q2-FY2006
- Milestone: Select ICM Pioneer Sites: Q3-FY2006
- Phase 3.1: Stage One - ICM Pioneer Site Concepts of Operations
and Requirements: Q4-FY2006 to Q4-FY2007
- Milestone: Select Pioneer AMS Sites: Q1-FY2008
- Decision Point No. 2: Site Application Feasibility: Are tools
available to model the ICM strategies, and do benefit-cost findings
warrant the implementation of ICM? Q1-FY2008
- Phase 3.2: Stage Two - Analysis, Modeling, and Simulation of
Selected Sites: Q2-FY2008 to Q1-FY2009
- Milestone: Select Pioneer Demonstration Sites: Q1-FY2009
- Decision Point No. 3: Site Demonstrations Feasibility: Are the
quality
and availability of ICM modeling and analysis data, the benefits
determined in the results, and the feasibility of the sites sufficient
to successfully demonstrate the potential of ICM? Q2-FY2009
- Phase 3.3: Stage Three - ICM Site Demonstration Projects:
Q2-FY2009 to Q4-FY2011
Phase 4: Knowledge and Technology Transfer: five items
- Phase 4.1: Develop ICM Resource Guide: Q2-FY2006 to Q4-FY2006; and
- Phase 4.1 continued: Update Resource Guide as Necessary:
Q2-FY2007 to Q1-FY2008 and beyond
- Phase 4.2: Develop ICM Knowledge and Technology Transfer Materials:
Q2-FY2008 to Q2-FY2009; and
- Phase 4.2 continued: Develop/Update ICM Knowledge and Technology
Transfer Materials: Q1-FY2010 to Q4-FY2011
- Phase 4.3: ICM Knowledge and Technology Transfer: Q2-FY2010 to
Q4-FY2011
Final Cross-Cutting Activities - Complete and Deploy Standards: one item
- Standards Completion, Deployment, and Updates: Q3-FY2004 to
Q4-FY2011
|
 |