Description of Figure 4

Integrated Corridor Management Roadmap for Phase 1

The graphic represents a detailed view of Phase 1: Foundational Research of the Integrated Corridor Management Roadmap.

Phase 1: Foundational Research is divided into eight items and spans from the third quarter, FY 2004 through the first quarter, FY 2006.

  • Phase 1.1: Develop Generic ICM Concept: Q2-FY2005 to Q3-FY2006
    • Generic ICM Concept of Operations: Q2-FY2005 to Q2-FY2006
    • Update Concept of Operations as Necessary: Q3-FY2006 to Q4-FY2006
    • Generic Corridor ICM Concept Requirements: Q4-FY2005 to Q3-FY2006
    • Update Requirements as Necessary: Q3-FY2006 to Q4-FY2006
    • ICM Planning and Implementation Guidance: Q3-FY2005 to Q2-FY2006
  • Phase 1.2: Conduct ICM Foundation Research: Q2-FY2005 to Q2-FY2006
    • Develop Alternative Definitions: Q2-FY2005 to Q4-FY2005
    • Develop a Process for Delineating a Corridor: Q2-FY2005 to Q2-FY2006
    • Relationship between Corridor Management and Regional Management: Q2-FY2005 to Q1-FY2006
    • Identify ICM Institutional Strategies and Administration: Q3-FY2005 to Q1-FY2006
    • ICM Program Planning and Funding: Q4-FY2005 to Q2-FY2006
  • Phase 1.3: Document Successful Local Integration Efforts: Q2-FY2005 to Q2-FY2006
    • Milestone: Post Request for Information (RFI): Q2-FY2005
    • Milestone: Close RFI: Q3-FY2005
    • Document RFI Responses: Q3-FY2005 to Q3-FY2005
    • Identification of Local Corridor Implementations for Site Visits: Q3-FY2005 to Q4-FY2005
    • Site Visits and Report: Q4-FY2005 to Q2-FY2006
  • Phase 1.4: Identify Corridor Types, Operational Approaches and Strategies, and Analysis Tools: Q3-FY2005 to Q3-FY2006
    • Development of Corridor Types: Q3-FY2005 to Q4-FY2005
    • Development of Operational Approaches: Q3-FY2005 to Q2-FY2006
    • Corridor Type and Operational Approach Selection Procedure: Q4-FY2005 to Q2-FY2006
    • Identify Cross Network Operational Strategies, Issues, and Needs: Q3-FY2005 to Q1-FY2006
    • Identify Cross Network Operational Strategies, Issues, and Needs: Q3-FY2005 to Q2-FY2006
    • Corridor Types, Op. Strategies, & Tools Report: Q1-FY2006 to Q2-FY2006
  • Phase 1.5: Determine ICM Development Feasibility: Q3-FY2005 to Q3-FY2006
    • Feasibility Analysis: Q3-FY2005 to Q2-FY2006
    • ICM Development Feasibility Briefing: Q3-FY2005 to Q4-FY2005
    • Decision Point No. 1: Development Feasibility: Are there sufficient integration issues and likelihood of success and benefits to justify further work? Q4-FY2005
    • ICM Development Feasibility Report: Q4-FY2005 to Q3-FY2006
  • Phase 1.6: Integrated Corridor Management Focus Groups: Q2-FY2006 to Q4-FY2006
    • Analysis, Modeling, and Simulation Focus Group: Q2-FY2006 and beyond
    • Technical Systems Integration Focus Group: Q2-FY2006 and beyond
    • Transit Focus Group: Q2-FY2006 and beyond
  • Phase 1.7: Provide Technical Assistance to ICM Stage 1 Pioneer Sites: Q2-FY2006 to Q3-FY2006
    • Tech. Assist. to ICM Pioneer Sites: Q4-FY2006 and beyond
  • Phase 1.8: Transit Issues, Contributions, and Perspectives in ICM: Q4-FY2006 to Q4-FY2007
    • Transit Issues, Contributions, and Perspectives: Q2-FY2006