Description of Figure 4

The graphic represents a detailed view of Phase 1: Foundational
Research of the Integrated Corridor Management Roadmap.
Phase 1: Foundational Research is divided into eight items and spans
from the third quarter, FY 2004 through the first quarter, FY 2006.
- Phase 1.1: Develop Generic ICM Concept: Q2-FY2005 to Q3-FY2006
- Generic ICM Concept of Operations: Q2-FY2005 to Q2-FY2006
- Update Concept of Operations as Necessary: Q3-FY2006 to
Q4-FY2006
- Generic Corridor ICM Concept Requirements: Q4-FY2005 to
Q3-FY2006
- Update Requirements as Necessary: Q3-FY2006 to Q4-FY2006
- ICM Planning and Implementation Guidance: Q3-FY2005 to Q2-FY2006
- Phase 1.2: Conduct ICM Foundation Research: Q2-FY2005 to Q2-FY2006
- Develop Alternative Definitions: Q2-FY2005 to Q4-FY2005
- Develop a Process for Delineating a Corridor: Q2-FY2005 to
Q2-FY2006
- Relationship between Corridor Management and Regional Management:
Q2-FY2005 to Q1-FY2006
- Identify ICM Institutional Strategies and Administration:
Q3-FY2005 to Q1-FY2006
- ICM Program Planning and Funding: Q4-FY2005 to Q2-FY2006
- Phase 1.3: Document Successful Local Integration Efforts:
Q2-FY2005 to Q2-FY2006
- Milestone: Post Request for Information (RFI): Q2-FY2005
- Milestone: Close RFI: Q3-FY2005
- Document RFI Responses: Q3-FY2005 to Q3-FY2005
- Identification of Local Corridor Implementations for Site Visits:
Q3-FY2005 to Q4-FY2005
- Site Visits and Report: Q4-FY2005 to Q2-FY2006
- Phase 1.4: Identify Corridor Types, Operational Approaches and
Strategies, and Analysis Tools: Q3-FY2005 to Q3-FY2006
- Development of Corridor Types: Q3-FY2005 to Q4-FY2005
- Development of Operational Approaches: Q3-FY2005 to Q2-FY2006
- Corridor Type and Operational Approach Selection Procedure:
Q4-FY2005 to Q2-FY2006
- Identify Cross Network Operational Strategies, Issues, and Needs:
Q3-FY2005 to Q1-FY2006
- Identify Cross Network Operational Strategies, Issues, and Needs:
Q3-FY2005 to Q2-FY2006
- Corridor Types, Op. Strategies, & Tools Report: Q1-FY2006
to Q2-FY2006
- Phase 1.5: Determine ICM Development Feasibility: Q3-FY2005 to
Q3-FY2006
- Feasibility Analysis: Q3-FY2005 to Q2-FY2006
- ICM Development Feasibility Briefing: Q3-FY2005 to Q4-FY2005
- Decision Point No. 1: Development Feasibility: Are there
sufficient integration issues and likelihood of success and benefits to
justify further work? Q4-FY2005
- ICM Development Feasibility Report: Q4-FY2005 to Q3-FY2006
- Phase 1.6: Integrated Corridor Management Focus Groups: Q2-FY2006
to Q4-FY2006
- Analysis, Modeling, and Simulation Focus Group: Q2-FY2006 and
beyond
- Technical Systems Integration Focus Group: Q2-FY2006 and beyond
- Transit Focus Group: Q2-FY2006 and beyond
- Phase 1.7: Provide Technical Assistance to ICM Stage 1 Pioneer
Sites: Q2-FY2006 to Q3-FY2006
- Tech. Assist. to ICM Pioneer Sites: Q4-FY2006 and beyond
- Phase 1.8: Transit Issues, Contributions, and Perspectives in
ICM: Q4-FY2006 to Q4-FY2007
- Transit Issues, Contributions, and Perspectives: Q2-FY2006
|
 |
 |
 |
 |