Description of Figure 5

The graphic represents a detailed view of Phase 2: Corridor Tools,
Strategies, and Integration of the Integrated Corridor Management
Roadmap.
Phase 2: Corridor Tools, Strategies, and Integration is divided into
two items and spans from the third quarter, FY 2006 to the fourth
quarter, FY 2011.
- Phase 2.1: ICM Tools and Strategies: Q2-FY2006 to Q4-FY2011
- Refine ICM Strategies: Q3-FY2006 to Q4-FY2006
- Develop ICM AMS Tools: Q4-FY2006 to Q3-FY2007
- Conduct the Analysis, Modeling, and Simulation of the Generic
Corridor: Q2-FY2007 to Q1-FY2008
- ICM Site Application Feasibility Report: Q4-FY2007 to Q1-FY2008
- Decision Point No. 2 – Site Application Feasibility: Are tools
available to model the ICM strategies, and do benefit-cost findings
warrant the implementation of ICM? Q1-FY2008
- Decision Point No. 3 – Site Demonstrations Feasibility: Are the
quality and availability of ICM modeling and analysis data, the
benefits determined in the results, and the feasibility of the sites
sufficient to successfully demonstrate the potential of ICM? Q2-FY1009
- ICM Tools, Strategies, and Implementation Final Report:
Q2-FY2010 to Q4-FY2010
- Phase 2.2: Prototyping ICM System Components: Q1-FY2007 to
Q4-FY2010
- Prototyping ICM System Components: Q1-FY2007 to Q4-FY2010
Updated
October 9, 2008 4:12 PM
|