The theory behind the staged statistical sampling design for the conduct of the acceptance test of the voice routing system is discussed in this section.
The acceptance test developed for this application begins with the following considerations.
Noting that the sample response measurements for this acceptance test fall into only two categories (success or failure), the acceptance test quantities can be related by the following equations, based on the binomial probability distribution:

From our initial requirements of the acceptance testing, we have established target values for p0 (0.01), α (0.05), p1 (0.05), and β (0.05). Since these equations produce discrete values, it is not necessarily possible to solve the two equations exactly for desired n and c. Instead, we develop a solution by fixing p0 and p1 and then experimenting with different values of n and c, searching for corresponding α and β reasonably close to the desired values.
For this particular acceptance test, an appropriate solution is found at n=147 and c=3 with p0=0.01, p1=0.05, α=0.06 and β=0.06. This leads to the following test:
The practical interpretation of this test is:
Reducing Tolerable Upper Limit
From the test above, true system failure rates between the p0 and p1 values are a problem because there is a definite risk in these cases that an acceptance sample will pass for these values when it should have failed. Therefore, it is desirable to make p1 as close as possible to p0. However, for a fixed p0, α, and β, this can only be done by increasing the sample size n. Modifying the acceptance sample plan above, p1 can be reduced to four percent for n=294 and c=6 with p0=0.01, p1=0.04, α=0.03 and β=0.05.
Though this acceptance test has slightly better α and β and is not exactly comparable to the original test, it does show that we essentially need to double the sample size to get a one percent reduction in the tolerable upper limit.
Staged Sequential Sampling
If acceptance samples are not collected all at one time, it may be possible to evaluate the sample results as they are obtained. The acceptance test criteria can be modified in this case to allow consideration of these interim sample results as a means of coming to an early conclusion of whether an acceptance test passes or fails. The general procedure would be to collect a predetermined number of samples and then evaluate the number of failures. If at or below a certain number, c1A, conclude the acceptance test passes. If at or above another number, c1R , which is greater than c1A, the acceptance test fails. If the number of failures falls between c1A and c1R then complete another stage of sampling. At the end of this second stage of sampling, compare the cumulative failures to a new set of acceptance limits to determine acceptance, failure, or continuation. This process can continue for as many stages as desired before reaching a final stage, where the cumulative number of failures from all stages is compared to a single acceptance limit, cT. If the cumulative total of failures from all stages is at or below the limit, the acceptance test passes. Otherwise, it fails.
If the desired acceptance plan has two stages of sampling, the previous equations can be modified to account for a potential additional stage of sampling by
A final solution that satisfies the equations above is n1=147, n2=147, c1A=1, c1R=5, cT=6 with p0=0.01, p1=0.04, α=0.06 and β=0.06. The test is completed as:
Relative to the single stage sample plan of 147 samples, this final sample plan provides the desired protection against the lower tolerable upper limit at four percent instead of five percent. However, it could require two stages, or 294 samples to achieve this. Relative to the single stage sample plan of 294 samples, this final sample plan provides the possibility of finishing sampling in half the total number of samples. However, its α and β are not quite as good as the single stage sample plan. Balancing these two considerations, the two-stage sample is recommended for this particular application.
| Week |
Dates |
Successful Call Deliveries |
Total Failures |
Average Delivery Time (Seconds) |
||
|---|---|---|---|---|---|---|
| AACN |
CAN |
SOS |
||||
19 |
2004.09.27-to-2004.10.03 |
0 |
4 |
21 |
0 |
0.76 |
20 |
2004.10.04-to-2004.10.10 |
0 |
4 |
31 |
0 |
0.91 |
21 |
2004.10.11-to-2004.10.17 |
0 |
1 |
32 |
0 |
1.00 |
22 |
2004.10.18-to-2004.10.24 |
1 |
2 |
37 |
0 |
0.80 |
23 |
2004.10.25-to-2004.10.31 |
0 |
11 |
27 |
0 |
0.79 |
24 |
2004.11.01-to-2004.11.07 |
0 |
5 |
19 |
0 |
0.71 |
25 |
2004.11.08-to-2004.11.14 |
0 |
6 |
40 |
0 |
0.85 |
26 |
2004.11.15-to-2004.11.21 |
1 |
2 |
40 |
0 |
0.77 |
27 |
2004.11.22-to-2004.11.28 |
0 |
7 |
21 |
0 |
23.25 |
28 |
2004.11.29-to-2004.12.05 |
1 |
0 |
21 |
0 |
0.64 |
29 |
2004.12.06-to-2004.12.12 |
|
|
|
|
|
30 |
2004.12.13-to-2004.12.19 |
0 |
0 |
36 |
0 |
0.89 |
31 |
2004.12.20-to-2004.12.26 |
0 |
5 |
33 |
0 |
0.84 |
32 |
2004.12.27-to-2005.01.02 |
1 |
6 |
32 |
0 |
0.82 |
33 |
2005.01.03-to-2005.01.09 |
0 |
7 |
26 |
0 |
0.91 |
34 |
2005.01.10-to-2005.01.16 |
0 |
2 |
36 |
0 |
0.71 |
35 |
2005.01.17-to-2005.01.23 |
0 |
5 |
36 |
0 |
0.80 |
36 |
2005.01.24-to-2005.01.30 |
1 |
4 |
22 |
0 |
0.93 |
37 |
2005.01.31-to-2005.02.06 |
0 |
0 |
37 |
0 |
0.81 |
38 |
2005.02.07-to-2005.02.13 |
0 |
3 |
21 |
0 |
0.96 |
39 |
2005.02.14-to-2005.02.20 |
0 |
3 |
26 |
0 |
0.86 |
40 |
2005.02.21-to-2005.02.27 |
0 |
1 |
29 |
0 |
0.77 |
41 |
2005.02.28-to-2005.03.06 |
0 |
0 |
25 |
0 |
0.84 |
42 |
2005.03.07-to-2005.03.13 |
1 |
0 |
30 |
0 |
0.81 |
43 |
2005.03.14-to-2005.03.20 |
0 |
5 |
22 |
0 |
0.96 |
44 |
2005.03.21-to-2005.03.27 |
1 |
2 |
19 |
0 |
0.91 |
45 |
2005.03.28-to-2005.04.03 |
0 |
1 |
27 |
0 |
0.75 |
46 |
2005.04.04-to-2005.04.10 |
0 |
1 |
30 |
0 |
0.84 |
47 |
2005.04.11-to-2005.04.17 |
1 |
2 |
25 |
0 |
0.79 |
48 |
2005.04.18-to-2005.04.24 |
0 |
0 |
15 |
14 |
0.80 |
49 |
2005.04.25-to-2005.05.01 |
0 |
0 |
0 |
36 |
0.00 |
50 |
2005.05.02-to-2005.05.08 |
|
|
|
|
|
51 |
2005.05.09-to-2005.05.15 |
|
|
|
|
|
52 |
2005.05.16-to-2005.05.22 |
1 |
2 |
36 |
0 |
0.82 |
53 |
2005.05.23-to-2005.05.29 |
0 |
1 |
21 |
0 |
0.91 |
54 |
2005.05.30-to-2005.06.05 |
3 |
5 |
40 |
0 |
0.90 |
55 |
2005.06.06-to-2005.06.12 |
|
|
|
|
|
56 |
2005.06.13-to-2005.06.19 |
|
|
|
|
|
57 |
2005.06.20-to-2005.06.26 |
0 |
3 |
38 |
0 |
0.83 |
58 |
2005.06.27-to-2005.07.03 |
0 |
4 |
32 |
0 |
1.64 |
59 |
2005.07.04-to-2005.07.10 |
0 |
4 |
41 |
0 |
0.76 |
60 |
2005.07.11-to-2005.07.17 |
1 |
2 |
22 |
0 |
0.84 |
61 |
2005.07.18-to-2005.07.24 |
1 |
15 |
23 |
0 |
0.79 |
62 |
2005.07.25-to-2005.07.31 |
0 |
11 |
30 |
0 |
0.85 |
63 |
2005.08.01-to-2005.08.07 |
3 |
1 |
46 |
0 |
0.78 |
64 |
2005.08.08-to-2005.08.14 |
|
|
|
|
|
65 |
2005.08.15-to-2005.08.21 |
0 |
2 |
0 |
0 |
1.00 |
66 |
2005.08.22-to-2005.08.28 |
0 |
1 |
0 |
0 |
1.00 |
67 |
2005.08.29-to-2005.09.04 |
0 |
5 |
0 |
0 |
0.60 |