Intelligent Transportation Systems
Printable Version

Light Vehicle and Heavy Truck Test
Track Verification Test Results

Outline

  • Introduction
  • Light Vehicle Test Track Verification Test Results
  • Heavy Truck Test Track Verification Test Results

Objectives of Track Verification Tests

  • Judge pass/fail of the system in crash-imminent tests for all valid test runs
  • Evaluate the consistency of system performance

Pass/Fail Judgment

  • Must meet pass/fail criteria in 8 out of 10 valid runs
  • Use of NIST Independent Measurement System (IMS) measures
  • Comparison between NIST IMS and UMTRI Data Acquisition System (DAS) measures - check on DAS accuracy and latency

Run Validity Assessment

  • Meeting run validity criteria in test procedures
  • Use of UMTRI DAS measures supplemented by NIST IMS
  • Verification with video images
  • Key variables of interest:
    • Longitudinal speed
    • Relative longitudinal speed
    • Lateral average speed
    • Range between host and lead vehicles @ brake onset by lead vehicle
    • Range between host and lead vehicles @ cut-in by lead vehicle
    • In-lane vehicle position

Breakdown of Light Vehicle Tests

  • Tests were conducted in September-October 2007
  • 5 LCW & 1 MT test were retested in February 2008

Breakdown of Heavy Truck Tests

  • All tests were conducted in September 2007
  • 4 LDW and 2 LCW tests were rested in November 2007
  • 1 FCW, 1 LDW, 3 LCW, 1 MT, and 1 NW tests were retested in March 2008