•Task 2:
–Final Assessment Report: 2/10/12
–Draft Stakeholder Input Report 2/16/12
–Draft Concept of Operations 3/28/12
–ConOps Walkthrough 5/11/12
–Final Concept of Operations 5/14/12
•Task 3
–Draft INFLO Requirements 6/22/12
–Requirements Walkthrough 8/7/12
–Final INFLO Requirements 8/21/12
•Task 4
–Draft Test Readiness Assessment: 9/18/12
Next Steps
Have only showed draft dates for Task 2-4 – final dates dependent on USDOT reviews, walkthroughs, revisions, etc. Blue dates indicate stakeholder-related items that will be dependent on stakeholder availability. These are ballpark dates for when the team would like to hold these sessions.