§3.
Execution of the Pre-Model Deployment Test
§The Test Conductor shall
conduct all of the interoperability tests defined
in the System Interoperability Test Plan, after:
□Installation
of the infrastructure components
□Availability
of the requisite number and types of vehicles, with trained drivers
§The Test Conductor
shall analyze the results of these tests and determine
whether any recommendations for modifications or enhancements
to any hardware or software components are required before
beginning the Model Deployment stage
§Based on current
interoperability activities by CAMP, additional modifications
may be required for devices and infrastructure
§With the approval of the
COTR, Model Deployment Stage begins