Pre-Model Deployment and Testing Stage
§3. Execution of the Pre-Model Deployment Test
§The Test Conductor shall conduct all of the interoperability tests defined in the System Interoperability Test Plan, after:
□Installation of the infrastructure components
□Availability of the requisite number and types of vehicles, with trained drivers
§The Test Conductor shall analyze the results of these tests and determine whether any recommendations for modifications or enhancements to any hardware or software components are required before beginning the Model Deployment stage
§Based on current interoperability activities by CAMP, additional modifications may be required for devices and infrastructure
§With the approval of the COTR, Model Deployment Stage begins