§Pre-Model Deployment Testing
– 12 months
□Preparation
for System Interoperability (~7 months)
□Execution
of System Interoperability Tests (~3 months)
□Development
of Recommendations for Enhancements and Modifications
to Safety Pilot Elements (~2 months)
□
§Model Deployment– 10-12
months
§
§Post Model Deployment
Activities – 6 months
□