§45 days after award –
Recipient submission of recommended updates to the
application specification.
§60 days after award –
Government will provide an updated application specification
(first specification update) and acceptance criteria in response to
industry inputs.
§6 months after award –
Recipient delivery of four (4) device units with self-certified
test results in accordance with the updated acceptance criteria, installation
and operating instructions, and all necessary hardware and cables to
provide for proper installation.
§6 months after award –
Recipient submission of pricing and delivery schedule
for potential future bulk procurement(s).
§7 months after award –
Government will provide the results of their acceptance
testing.
§8 months after award –
Recipient submission of updated four (4) device units
based on results of the initial acceptance tests
§10 months after award –
Government will provide the results of their final round of
acceptance testing based on the updated device and establish a QPL of
acceptable devices.