U.S. Department of Transportation
Triscallion_Black
Transit Connected Vehicle Safety Pilot Roadmap
(rev. 07/2011)
CY 2010
CY 2011
CY 2012
Q1
Independent Evaluation of Testing Activities
CY 2013
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Transit Vehicle Safety Policy Review
Pre-Model Deployment  Testing
1B. Apps. Concept Development
1A. Safety Application Identification
Model Deployment Full Scale Testing
Transit Stakeholder Mtg.
1D. Project Procurement
1E. Application and  Retrofit Device Development & Testing
Retrofit Transit Vehicles to Test Conductor
Coordination of Infrastructure Specifications with Test Conductor (as needed)
2A. Transit Simulator Assessment
2B. Procurement for Driver Clinics OR Simulator Dev.
NOTE: Model Deployment schedule based on Safety Pilot Roadmap rev. 21
Transit Connected Vehicle Stakeholders Outreach and Engagement
CoordinationCoordination
2012 APTA Bus Conf.
Transit Connected Vehicle Preliminary ConOps Results
Award(s)
Contract (Ops IDIQ) Award
1F. Retrofit Veh. Build, Testing, Driver Prep & Support
Contract Award(s)
1G. Training Material Dev. & Delivery
Safety Pilot Test Conductor Contract Award
Coordination with Safety Pilot Test Conductor and Independent Evaluator Regarding Transit Safety Applications
2011 TransITech
1C. Project Scoping
2C. Transit Driver Clinics and Evaluation
Simulator Input to Application Development