Activity
Completion Date
Project and Systems Engineering Management
Ongoing
Stakeholder Outreach
Ongoing
Applications Assessment of Deployed Systems
October 2011
Applications Assessment of Research Projects
October 2011
SRI Concept of Operations
May 2012
SRI System Requirements
October 2012
SRI System Architecture
October 2012
SRI Component-Level Design
February 2013
SRI Development and Testing
April – June 2013
SRI Build and Install
June 2013
SRI Prototype Testing
August - September 2013
SRI Final Documentation
December 2013