TASK 5 – TIMELINE
•Task 5 – Security Management of the V2V-Interoperability Project consists of the following subtasks:
•Subtask 1: Security Framework ü
•Subtask 2: System Requirements ü
•Subtask 3: Build Prototype System
•Subtask 4: System Test
•Subtask 5: Integration with Scalability Test Bed
•
• Task 5 Timeline
2010
2011
2012
Subtask 1
Security
Framework
Subtask 2
Security
Requirements
Subtask 3
Build Prototype
System
Subtask 4
System
Test
Subtask 5
Integration with
Scalability Testbed