Pre-Model Deployment
Model Deployment
IV&V of Security Plan, Devices, Installation
Design Completed (SW 1 & 2)
Develop and Hosting of
 Security Credential Management System
Agreement Executed
Build Prototype V-V System
Integration w/ Scalability TB
CAMP Prototype Completed
SOW for SCMS
SCMS Integration Test
Security Profiles Completed
Assessment of Complete Plan
System Test
SCMS Site Investigation Completed
Security Credential Batch Tool
Site Security Plan
Security Credential Processes Defined
Final SCMS Deployed
Security Plan Roadmap v5
Device Specifications
Security Plan
•Builds on work initiated under agreements with CAMP – concentrated on cryptographic process for signing a BSM and the process for managing the cryptographic material.
•Started an overall plan for the installation – all elements of the system.
•Includes USDOT and 4 external groups/contractors – embodied in device specifications, operating practices.
•All parts need to be in place by the start of the Model Deployment – August 21, 2012.