CY 2010
1Q
2Q
3Q
4Q
CY 2011
1Q
2Q
3Q
4Q
CY 2012
1Q
2Q
3Q
4Q
CY 2013
1Q
2Q
3Q
4Q
CY 2014
1Q
2Q
3Q
4Q
SPaT Prototype
RG&I Trade Study
Positioning Prototype
Test and Evaluation
Final SPAT Interface Definition & Policy Guidance
SPaT I/F Definition
Mapping Prototype
V2I Security Reqs
CY 2009
1Q
2Q
4Q
3Q
Application Cert Reqs
SPaT I/F Review

Applications Certification Requirements:
•Ensure applications meet requirements of IntelliDriveSM Program.
•A systems approach to certification of applications.
•This is NOT an equipment certification process.
V2I for Safety Roadmap – Draft
Track 3
Infrastructure Communications & Interoperability
Integrated V2I Infrastructure
System
Comms Reqs
Comms TS
The Applications Certification Requirements project is required to ensure V2I safety applications meet the requirements of the IntelliDrive program.

•Applications will involve multiple components, including potentially hardware, firmware, software and algorithms. The Applications Certification Requirements will describe how certification of these    systems should be approached.
oThe project will not provide a certification process for any given component.
oAn equipment certification process is being developed elsewhere under the IntelliDrive program.
oEquipment certification alone is not adequate for the certification of applications.

•Project progress:
oThe anticipated start date for this effort is 2nd quarter 2011 with completion in 2nd quarter 2012.
oThe project will be documented with a report that establishes certification requirements for V2I safety applications.