JPO Program Status Reports Feb 08

 

STATUS INDICATOR DEFINITIONS

 

G

Y

R

COST

Program Within Budget

Program Costs >1% but < 10% Over Budget

Program Costs > 10% Over Budget

SCHEDULE

Goal Achievement On Time

Goal Achievement 1 to 4 Weeks Late

Goal Achievement > 1 Month Behind Schedule

PERFORMANCE

Goals/Major Objectives Will Be Achieved

Goals/Several Major Objectives In Jeopardy

Goals Will Not Be Achieved


Program Title: CICAS

JPO Program Manager: Schagrin

Current Updates (as of 2/8/08):

Program is currently underway with prime objectives being accomplished.

Program Description Summary

The CICAS Initiative is designed to employ a combination of vehicle-based technologies and systems, infrastructure-based technologies and systems, and communications systems focused on detecting and avoiding potential crossing-path crashes at intersections. CICAS will combine these technologies, thereby creating three innovative applications: an application that warns drivers of potential signal or stop sign violations, an application that assists the driver’s decision making capability when proceeding onto a high speed road after making a legal stop at a stop sign, and an application that assist the driver’s decision making capability when turning left in the face of oncoming traffic. The major focus of this initiative is to determine if these systems are effective at reducing crossing path crashes while achieving a sufficient level of driver acceptance.

Program Goals

  • Signal and stop sign violation field operational test.
  • Prototype system developed for stop sign assist.
  • Prototype system developed for signalized left turn assist.
  • Safety benefits assessments.

Program Status (as of2/8/08)

Cost

Schedule

G

 G

Original Budget:

$ 43,477,450

Current PoP (Months):

(48 months)

 

Current Budget

$ 39,494,640

Original PoP:

5/06-9/10

FY 08 Budget

$ 4,600,000

 

 

Obligated:

$ 19,797,418

Mod:

Mod to extend Phase 1 CICAS-V by 3 months.

Expended to Date:

$ 9,938,981

Mod:

SSA and SLTA being descoped to no longer include an FOT

Amount Remaining:

$ 9,858,437

 

 

Performance G (as of 2/8/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Signal and stop sign violation:

  • Prototype developed; go/no-go decision to begin field test
  • Signal and stop sign violation: Field test and benefits assessment completed

 

Aug 2008

 

Sept 2010

 

 

Signalized left turn assist:

  • initial research completed; go/no-go decision to begin field test
  • prototype developed; go/no-go decision to begin field test

 

Sept 2008

 

Aug 2009

 

 

 

 

 

 

Management Summary

% Program Schedule Elapsed:

24 % (as of Dec 07 )

% Program Budget Expended:

25 % (as of Dec 07)

Issues

  • Question whether the CICAS-V FOT is of sufficient value to warrant an investment of $15M.
  • CICAS-SSA and SLTA being descoped to no longer include a field operation test under the current CICAS structure.

Program Title: Clarus
FHWA Program Manager: Paul Pisano
JPO Program Manager and COTR: Ben McKeever

Current Updates (as of 1/31/08):

  • Reviewing Concept of Operations (ConOps) Submittals for the Regional Demonstrations
  • Received final ConOps on 1/31/08
  • Preparing RFP for next phase of demo

Program Description Summary

The Clarus Initiative will develop and demonstrate a high resolution, integrated surface transportation weather observing, forecasting, and data management system; and will establish partnerships to create timely, accurate, and relevant weather and road condition information for transportation users and operators.

Program Goals

  • Design, develop and demonstrate the assimilation, quality checking, and data dissemination capabilities captured within the Clarus system
  • Work with our public and private partners to develop and evaluate the value-added road weather information products that Clarus enables
  • Improve mobility and safety by enabling travelers to make informed decisions on when, where, and how to travel because of adverse weather
  • Work with NOAA to move from demonstration to deployment of a nationwide network

Program Status (as of1/31/08)

Cost

Schedule

G

Original Program Budget:

$11.5 million

Current PoP (Months):

( 72 months)

10/01/05 – 9/30/10

Current Program Budget:

$15.9 million

Original PoP:

10/01/04 – 9/30/09

FY 08 Budget:

$4.8 million

 

 

Obligated:

$7.7million

Mod 1:

9/30/10

Expended to Date:

$7.7 million

 

 

Amount Remaining:

$8.2 million

 

 

Performance G (as of 1/31/08)


Major Objectives/Deliverables

Original Schedule

Actual

Date Revised

Establish Stakeholder Participation

September 2004

September 2004

 

System Design

December 2006

December 2006

 

System Proof of Concept

December 2006

December 2006

 

Regional Demonstration Con Op

January 2008

On Schedule

 

Complete Phase 3 Regional Demonstration

September 2009

(revised to Sept. 2010)

On Schedule

May 2007

Thirty-three states connected to Clarus

September 2010

On Schedule

 

Transition system operations to NOAA

September 2010

On Schedule

 

Management Summary

% Program Schedule Elapsed:

43% (as of 1/31/08)

% Program Budget Expended:

48% (as of 1/31/08)

Issues

  • Procurement timeline was protracted and caused a delay of one year in the Regional Demonstrations
  • Lack of definition within NOAA on their system development may delay the Clarus transition to NOAA; however, a recent meeting with National Weather Service management confirms their support for this objective
  • Awaiting definition/development of the flow of data from VII in order to bring vehicle-based observations into the Clarus System

Program Title: Congestion Initiative, ITS-OTMC

JPO Program Manager - Brian Cronin (Overall Coordination, SF, NY, Miami and Evaluation)
JPO Leads – Linda Dodge ( Seattle and Minnesota)
JPO Leads – Yehuda Gross ( San Diego)

Current Updates (as of 02/01/08):

Currently working to obligate ITS funds. Except for San Diego, obligations are conditional on sites receiving legal authority to price. Evaluation contractor recommendation provided to contracts on 01/25/08.

Program Description Summary

In May 2006, the U.S. Department of Transportation (USDOT) announced its National Strategy to Reduce Congestion on America’s Transportation Network (the Congestion Initiative), a bold and comprehensive national program to reduce congestion on the Nation’s roads, rails, runways and waterways. The Intelligent Transportation Systems (ITS) Operational Testing to Mitigate Congestion (ITS-OTMC) Program provides the advanced technology foundation for the Congestion Initiative. ITS technologies will support congestion pricing, improved system operations and performance, regional efforts to expand provision of real-time traveler information, improved traffic incident response, improved arterial signal timing and reduced obtrusiveness of highway construction work zones. The overall objective of the ITS-OTMC Program is to facilitate the operational testing and evaluation of innovative and aggressive congestion reduction strategies incorporating ITS technologies that can demonstrate measurable reductions in congestion levels in the deployment areas.

Program Goals

  • Demonstrate impact on congestion through the implementation of tolling, transit, technology and telecommuting strategies (The 4 T’s).
  • Demonstrate impact of technology to enable variable pricing.
  • Evaluate the urban partner demonstrations.
  • Develop outreach materials to educate the industry on the benefits of the 4 T’s.

Program Status (as of01/01/08)

Cost

Schedule

G

 G

Original Program Budget:

$ 100,000,000

Current PoP (Months):

12/8/06 – 6/30/11

Current Program Budget

$100,000,000

Original PoP:

2/28/05 – 8/1/11

FY 08 Budget

$40,000,000

 

 

Obligated:

$8,600,000

 

 

Expended to Date:

$ 0

 

 

Amount Remaining:

$100,000,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Performance G (as of 02/01/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Select Urban Partners

8/8/07

8/8/07

 

Obtain Legislative Authority

3/31/08 – 5/30/08

 

Select Evaluation Contractor

3/31/08

 

 

Complete Evaluation Plans for Urban Partners

9/30/08

 

 

Systems Operational

9/30/09

 

 

Complete Evaluation Report

5/30/11

 

 

 

 

 

 

 

 

 

 

Management Summary

% Program Schedule Elapsed:

20% (as of 02/01/08)

% Program Budget Expended:

0% (as of 01/01/08)

Issues

  • Schedule reflects nine months for selection process and 6 months for initial award of funds.
  • $8.6 million obligated in 2007 to San Francisco, although they are not allowed to spend until legislative authority is obtained in March 31, 2008.
  • Legislative authority for New York must be by March 31, 2008.
  • Legislative authority for Seattle is anticipated to be by the end of March 2008. Per the signed term sheet, Seattle is not allowed to drawdown funds until the system is implemented, which is September 30, 2009. Seattle is scheduled to receive $47 million of ITS funds. This will significantly impact reporting on the expenditures to date.
  • San Diego is receiving $3 million to support an innovative guided bus application. FTA has the lead in negotiating the overall program. (They have $15 million in the project.) We anticipate a May award.
  • The evaluation contract is about to be awarded. Miami is not receiving ITS funds, and is doing a self-evaluation. JPO staff are providing guidance to Miami on their evaluation. Miami’s project is expected to be in operation for the first phase during the summer of 2008.
  • See attached file for more specific funding profile and status of the ITS funds.

Program Title: Electronic Freight Management Evaluation

JPO Program Manager: Kate Hartman

 

 

 

Current Updates (as of 02/11/08):

SAIC continued to fully implement its evaluation data collection and analysis activities. This included significant follow-up interviews and data requests from the project partners, including the Hong Kong participants. SAIC provided an Interim Evaluation Update at the Intermodal Freight Technology Working Group Meeting in Atlanta, Georgia. SAIC has been having regular telecons to discuss progress.

Program Description Summary

The Electronic Freight Manifest (EFM) initiative combines the successful elements of the air cargo tests and the IFTWG’s Freight Information Highway Test and is designed to enhance freight transportation productivity through the intelligent application of technology enhancements. The EFM deployment project is composed of three distinct phases - Design and Development, Deployment, and Operations. The evaluation effort is expected to mirror these phases. During the Design and Development Phase of the underlying EFM deployment, the evaluation contractor similarly designed and developed the evaluation framework. It included the design of the overall evaluation strategy, analysis of preliminary data, and

Program Goals

The deployment of the EFM will result in:

  • A more efficient supply chain
  • Improved logistics performance and visibility
  • A more secure supply chain
  • More efficient regulatory and trade compliance.

Program Status (as of09/07/07)

Cost

Schedule

G

G

Original Budget:

$999,815

Current PoP (Months):

(45 months)

4/1/05 – 12/31/08

Current Budget

$999,815

Original PoP:

4/1/05 – 12/31/07

FY 08 Budget

$0

 

 

Obligated:

$999,815

Mod 1:

Thru 12/31/08

Expended to Date:

$540,656

 

 

Amount Remaining:

$459,159

 

 

Performance G (as of 09/07/07)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Project Kick Off

5/11/05

6/27/05

 

Evaluation Strategy Briefing

7/13/05

9/13/05

 

Evaluation Plan

8/30/05

1/19/06

 

Detailed Test Plans (Draft)

11/10/05

6/12/07

 

Detailed Test Plans (Final)

12/22/05

10/5/07*

 

Draft CEFM Final Report

3/08

 

 

Evaluation Final Results Briefing

3/08

 

 

Draft JPO Lessons Learned Report

4/08

 

 

Final CEFM Final Evaluation Report

5/08

 

 

Final JPO Lessons Learned Report

6/08

 

 

Draft CEFM Deployment Eval Report

9/08

 

 

Final CEFM Deployment Eval Report

11/08

 

 

Management Summary

% Program Schedule Elapsed:

74% (as of 12/31/08)

% Program Budget Expended:

54% (as of 12/31/08)

Issues

  • None.
  • (*Not an issue, but an explanation for slippage in evaluation test plan delivery was due to issues identified when synching up with the Op Test as Evaluation work was awarded before final Op Test plan had been developed and apporoved.)

Program: Emergency Transportation Operations (ETO)

JPO Program Manager: Linda Dodge

Current Updates (as of 02/08/08):

In the process of packing ETO documents completed to date into a CD with products developed as part of the Public Safety Program.

Currently assessing a subset of tools selected from the modeling inventory. This assessment will be more detailed than the inventory and will categorize modeling approaches along a continuum of geographic scale as well as computational complexity.

Program Description Summary

The ETO was launched in 2004 with the goal of improving the speed and effectiveness of response to major incidents and management of those incidents.

Program Goals

To accomplish this ETO concentrated on providing the tools, procedures, and information that can be used to actively manage and therefore expedite the safe progress of an evacuation.

Program Status (as of02/08/08 )

Cost

Schedule

G

G

Original Program Budget:

$5,900,000

Current PoP (Months):

n/a

Current Program Budget

$353,102.85

follow on

 

Original PoP:

varied project

(aprx. 14 proj. in original Initiative

FY 08 Budget

$0 new money

 

 

Obligated:

$353,000

$102.85 uncommitted

 

 

Expended to Date:

$5,500,000

 

 

Amount Remaining:

$102.85

 

 

Performance Y (as of 02/08/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Camera Phone Proof of Concept Project Final Report (Orig. initiative)

Fall 2006

July 30, 2007

 

Follow on:

Evacuation Management Operations (EMO) Modeling Assessment:
Transportation Modeling Inventory

28 May 2007

13 December 2007

 

Evacuation Model Users Guide

1 August 2008

1 August 2008

 

Best of Public Safety / ETO CD

1 May 2008

1 May 2008

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Management Summary

% Program Schedule Elapsed:

100% (as of 02/08/08); 75% of follow-on

% Program Budget Expended:

100% (as of 02/08/087) [$102.85 remains of follow-on]

Issues

Original Initiative issues:

  • Delayed kick-off of one of the sub-projects with DOJ partner
  • Camera pone sub-project with CapWIN had GSA related delays due to negotiations to purchase “test” phones and service; which was compounded by the sudden death of one of the primary team members.

NOTE: all delays have been resolved to date.

Program Title: Integrated Corridor Management (ICM)

JPO Program Manager - Brian Cronin
FHWA Manager – Dale Thompson
FTA Manager – Steve Mortensen

Current Updates (as of 02/01/08):

On January 31, 6 of 8 ICM Pioneer Sites delivered their Draft Requirements Documents. The deliverable will be the final Pioneer Site deliverable for Stage 1. An ICM analysis, modeling, and simulation test corridor report will be completed in February.

Program Description Summary

The ICM Initiative will demonstrate how operational approaches and multimodal ITS solutions can be applied to proactively manage the movement of people and goods through major metropolitan transportation corridors. The Initiative will facilitate deployment of integrated corridor management systems by providing guidance on shifting travel demand to available capacity by delivering real-time travel data through in-vehicle devices, changeable message signs, and 511 services.

Program Goals

  • To provide the institutional guidance, operational capabilities, and ITS technical methods needed for effective Integrated Corridor Management Systems
  • Conduct foundation analysis to define ICM. (Completed)
  • Partner with Pioneer Sites to Define ICM Systems along real corridors (Concept of Operations and Requirements)
  • Develop tools to analyze, model and simulate the impacts of ICM strategies implemented along corridors
  • Demonstrate ICM systems and evaluate their impacts on congestion

Program Status (as of01/01/08)

Cost

Schedule

G

 Y

Original Program Budget:

$41,625,000

Current PoP (Months):

2/28/05 – 12/30/11

Current Program Budget

$37,410,645

Original PoP:

2/28/05 – 10/27/11

FY 08 Budget

$ 3,950,000

 

 

Obligated:

$ 400,000

 

 

Expended to Date:

$ 9,859,961

 

 

Amount Remaining:

$27,550,684

 

 

Performance G (as of 02/01/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

ICM Foundation Analysis

3/31/2006

4/18/2006

4/18/2006

ICM Pioneer Site Con Ops

3/27/2007

6/22/2007

6/22/2007

ICM Pioneer Site Requirements

9/26/2007

 

3/31/2008

ICM AMS Site Feasibility Report

8/31/2007

 

3/31/08

ICM Pioneer Site AMS Complete

11/14/2008

 

9/1/2009

ICM Demonstration Award

9/29/2008

 

8/1/2009

ICM Demonstration Complete

10/27/2011

 

12/30/11

ICM Knowledge and Tech Transfer Final

7/13/2011

 

12/30/11

Management Summary

% Program Schedule Elapsed:

43% (as of 02/01/08)

% Program Budget Expended:

26% (as of 01/01/08)

Issues

  • Funding reallocation in Spring 2007 resulted in extending the funding profile into FY 2010. Overall budget was reduced. We do not expect significant additional schedule slippage.
  • There was a significant schedule slippage to allow the contracting process for the Pioneer Sites to be completed. We are taking steps to streamline this approach for future stages. Since November 2007, the start of the Pioneer Site work, we are three months behind schedule.
  • We intentionally let the schedule slip approximately three months in 2008 to allow the Pioneer Sites to improve the quality of their concepts of operations and requirements documents. We anticipate working on the demonstration phase partly in parallel with the AMS phase to pick up on the schedule slippage.
  • Due to budget reallocation, we have reduced the number of sites to model from up to 4 to up to 3. We also anticipate that the demonstration phase will be up to 3 (probably 2) instead of up to 4 sites.
  • Modeling phase schedule also slipped three months, but it was not in the critical path.

Program Title: Integrated Vehicle-Based Safety Systems (IVBSS)

JPO Program Manager: Steve Sill
NHTSA Technical Manager: Jack Ference

Current Updates (as of 02/01/08):

This report reflects verbal direction given by the RITA administrator at the December 21, 2007 Phase II Go-No/Go milestone decision meeting. The direction was to extend Phase I to demonstrate that the prototype light vehicle and heavy truck IVBSS fully meet project performance requirements. $361K in additional funding for the Phase I extension to be provided using JPO contingency funds.

Program Description Summary

The purpose of this program is to develop and field test an integrated, vehicle-based safety system addressing rear-end, lane change and road departure crashes for light vehicles and heavy commercial trucks.

Program Goals

  • Develop an integrated, vehicle-based safety system and verify that the system meets performance requirements and is ready for use by volunteer drivers and truck fleets in an extended field test.
  • Conduct a field test to determine system effectiveness, potential safety benefits, and user acceptance of the prototype integrated systems.
  • Share key documents (functional requirements, performance guidelines, test procedures) and research findings (human factors and drive-vehicle interface experimental results and field test results) with the automotive and heavy truck industry.

Program Status (as of 02/01/08)

Federal Costs*

Schedule (as of 02/01/08)

G

Original Program Budget:

$35,428,000

Current PoP (Months):

11/23/05 – 04/30/10 (53 months)

Current Program Budget:

$35,769,990

Original PoP:

11/23/05 – 11/30/09

(48 months)

Obligated:

$32,428,000

 

Expended to Date:

$21,282,702

 

 

Amount Remaining:

$11,145,298

 

 

*Reflects most recent costs reported by contractors/grantees, delayed up to 60 days.

 

 

Performance G (as of 02/01/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Human Factors and DVI Summary Report

11/30/07

12/03/07

 

Preliminary FOT Report delivered*

11/30/07

 

04/15/08

Phase I Interim Report delivered*

01/15/08

 

04/15/08

Light Vehicle Verification Testing completed - Phase I extension (*new)

03/01/08

 

 

Heavy Truck Verification Testing completed – Phase I extension (*new)

03/15/08

 

 

* due dates reflect adjustment due to Phase I (4-month) extension (December 31, 2007 to April 30, 2008)

Management Summary

% Program Schedule Elapsed:

49%

% Program Budget Expended:

59% ( Reflects most recent costs reported by contractors/grantees, delayed up to 60 days.)

Issues

  • Request for formal approval of Phase I extension directed by RITA Administrator approved after substantial delay. Light vehicle team members (UMTRI, Visteon and Cognex) are currently operating at-risk by their own choice (~$261K effort) since January 1. Contracting efforts to provide additional funding as approved by RITA Administrator on 01/28/08 may delay program further.
  • Request for Citizant FY08 funding has not been approved. Contractor operating at risk since October 2007. Further delay in funding obligation will jeopardize project execution.
  • Execution of IVBSS Annual Public Meeting (April 10-11, 2008) is threatened due to delay in renegotiation and award of ITSA 2008 contract and RITA Administrator approval of and award of required funding. ITSA and Citizant are key organizations supporting this outreach effort.

Program Title: Mobility Services for All Americans (MSAA)

JPO Program Manager: Yehuda Gross

 

 

 

 

Current Updates (as of 02/01/08):

On January 23-24, 2008, the USDOT hosted the demonstration phase 1 mid-term workshop in Alexandria VA. The eight phase 1 sites presented their system concept of operations and shared useful lessons learned with each other. The USDOT took the opportunity to clarify requirements and expectations with respect to the project and provide an outlook for the phase 2 of the demonstration.

Program Description Summary

To address growing concerns over rising costs and to improve service, the Mobility Services for All Americans (MSAA) initiative aims to bring all communities together in a coordinated effort to apply technological solutions to the barriers of accessibility and mobility for the transportation disadvantaged. Proper use of ITS applications can improve delivery of human service transportation by boosting service productivity, facilitating service coordination, and enhancing system accessibility.

Program Goals

  • Demonstrate the technical and institutional feasibility of coordinated human service transportation systems using ITS applications.
  • Develop a comprehensive stakeholders outreach and knowledge transfer plan based on needs identified and prioritized by stakeholders
  • Conduct high priority ITS outreach and knowledge transfer products and activities to promote program impacts and institutional acceptance.

Program Status (as of02/01/08)

Cost

Schedule

G

Original Program Budget:

$9,000,000

Current PoP (Months):

(69 months)

10/01/04 – 06/30/10

Current Program Budget

$9,000,000

Original PoP:

10/01/04 – 03/31/09

FY 08 Budget

$3,500,000

 

 

Obligated:

$4,334,828

Mod 1:

- 06/30/10

Expended to Date:

$1,954,675

 

 

Amount Remaining:

$2,380,153

 

 

Performance G (as of 02/01/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

TMCC Concepts of Operations (8)

11/30/06

10/31/07

 

TMCC System Designs (8)

09/30/07

 

06/30/08

MSAA Stakeholder Outreach Plan

09/30/08

 

 

TMCC Institutional Evaluation Report

 

 

03/31/09

TMCC System Deployments (2)

12/31/08

 

12/31/09

TMCC System Impacts Evaluation

 

 

06/30/10

Management Summary

% Program Schedule Elapsed:

58% (as of 02/01/08)

% Program Budget Expended:

% (as of 02/01/08)

Issues

  • All program goals and major objectives remain intact and will be achieved.
  • The initiative experiences 12 months delay from original schedule due to:
    • 3 months, expansion of foundation research scope to accommodate more listening sessions and focus groups, and to develop generic ConOps.
    • 4 months, discussion/negotiation with UWR for joint demonstration (including time to make UWR funds available).
    • 5 months, FTA internal process to approve/process cooperative agreements.
  • The 12-month delay has been reduced to 9 months by shortening the period of performance for Phase 1 demonstration from 18 months to 15 months.
  • However, similar administrative oversight requirements and approval process (i.e., further delays) are possible for Phase 2 sites selection and announcement.

Program Title: Next Generation 9-1-1 (NG9-1-1)

JPO Program Manager: Linda Dodge

Current Updates (as of 02/08/08):

From a set of more than 50 applicants, DOT selected five 9-1-1 call centers or authorities to participate in this Spring’s NG9-1-1 proof-of-concept demonstration.

Program Description Summary

To enable the general public to make a 9-1-1 “call” (any real-time communication – voice, text, or video) from any wired, wireless, or Internet Protocol (IP)-based device, to the PSAP, and enable data sharing with the emergency communication network.

Program Goals

  • Develop a national architecture and high-level design for NG9-1-1 System
  • Conduct a Proof of Concept Demonstration
  • Prepare a transition plan for NG9-1-1 implementation

Program Status (as of02/08/08 )

Cost

Schedule

G

Original Program Budget:

$6,056,614

Current PoP (Months):

24

Current Program Budget

$5,381,614

Original PoP:

24

FY 08 Budget

$675,000

 

 

Obligated:

$454,000

 

 

Expended to Date:

$ 3,153,873

 

 

Amount Remaining:

$1,945,127

 

 

Performance Y (as of 02/08/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Draft System Design Document

17-Sep-07

15-Nov-07

8-Nov-07

Critical Design Review (PDR) Meeting

17-Sep-07

15-Nov-07

15-Nov-07

Interim System Design Documents

29-Oct-07

Under Revision

18-Jan-08

Final Proof-of-Concept Deployment Plan

12-Nov-07

Under Revision

18-Jan-08

Final Summary Report of Call Taker HMI and Human Factors Issues

1-Oct-07

28-Nov-07

6-Nov-07

Final HMI Design Document

12-Nov-07

16-Jan-08

18-Jan-08

Benefit-Cost Analysis Report

18-Jun-07

11-Jan-08

18-Jun-07

Transition Issues Report

2-Jul-07

5-Feb-08

25-Jan-08

Preliminary Transition Plan

21-Jul-08

 

21-Jul-08

Management Summary

% Program Schedule Elapsed:

54% (as of 02/08/08)

% Program Budget Expended:

52% (as of 02/08/087)

Issues

 

Program Title: VII

JPO Program Manager: Schagrin

Current Updates (as of 02/8/8):

 

Program Description Summary

The VII Initiative is a cooperative effort between USDOT, State governments, and the automobile industry. The initiative will develop and test an information infrastructure that uses advanced communications technologies to exchange real-time information between the roadside and vehicles and between vehicles to improve safety and mobility. Applications are being developed to test multiple safety and mobility uses of VII. VII seeks to achieve significant reductions in vehicle crashes through safety applications and vehicle delay through State and local management of the surface transportation network enhanced by real-time traffic information and improved transportation systems operation. VII seeks to determine the technical feasibility, economic viability, and social acceptability of a coordinated, nationwide communications system deployed on the road infrastructure, and installed in all vehicles sold in the US.

Program Goals

  • Establish developmental test environments in Detroit and California.
  • Generate technical data to support deployment decision making process.
  • Develop a policy framework to establish a viable business model
  • Develop a cost-benefit analysis,
  • Define viable deployment strategies
  • Perform institutional issues analyses to support a deployment decision making process.
  • Perform a privacy and security policy analyses to support deployment decision making process
  • Develop application tools to support public agency needs for real time road network data
  • Monitor technology developments to continually enhance system road network performance

Program Status (as of02/08/08)

Cost

Schedule

Y

Original Budget:

$ 91,273,359

Current PoP (Months):

(xx months)

 

Current Budget

$ 93,331,859

Original PoP:

8/05-12/10

FY 08 Budget

$ 22,000,000

 

 

Obligated:

$ 88,076,811

Mod 1:

Expended to Date:

$ 67,002,861

 

 

Amount Remaining:

$ 21,073,950

 

 

Performance Y (as of 02/08/08)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

Currently rescoping and rebaselining the VII program.

Dec 2007

 

March 2008

Establishing Volpe Tiger Team for developing and executing initial deployment capability

Jan 2008

Jan 2008

 

Begin proof of concept testing of infrastructure, vehicles and applications in Detroit and California.

Jan 2008

February 2008

 

Proof of Concept testing complete.

March 2008

 

May 2008

Preliminary analyses of business model and institutional issues.

May 2008

 

 

Initial deployment operational

Dec 2008

 

 

Management Summary

% Program Schedule Elapsed:

% (as of )

% Program Budget Expended:

% (as of )

Issues

  • Need to rescope program to be more flexible and adaptive to technology option as opposed to just DSRC
  • Need to create an institutional framework and business model that will be supportive of VII deployment

Program Title: VSCA (V2V)

JPO Program Manager: Schagrin

Current Updates (as of 2/8/08):

Project remains on schedule and within budget.

Program Description Summary

The VSCA program is a collaborative effort between the US DOT and a consortium of five automobile manufacturers (DaimlerChrysler, Ford, General Motors, Honda, and Toyota) to explore the use of vehicle-to-vehicle (V2V) wireless communication to improve the effectiveness of vehicle collision avoidance systems.

Program Goals

  • The goal of the VSC-A program is to develop and test communications-based vehicle safety systems to determine if dedicated short range communications (DSRC) at 5.9 GHz, in combination with vehicle positioning can improve sensor-based safety systems and/or enable new communications-based safety applications

Program Status (as of09/07/07)

Cost

Schedule

G

Original Budget:

$11,106,000

Current PoP (Months):

(36 months)

 

Current Budget

 

Original PoP:

12/06-11/09

FY 08 Budget

$ 4,897,000

 

 

Obligated:

$ 3,750,000 (plus Volpe)

Mod 1:

Expended to Date:

$ 1,245,069

 

 

Amount Remaining:

$ 2,804,931

 

 

Performance G (as of 09/07/07)

Major Objectives/Deliverables

Original Schedule

Actual

Revised

  • Problem scenarios and safety application selection

June 2007

June 2007

 

  • System concepts of operation and performance requirement

March 2007

March 2007

 

  • Level I test bed implementation

June 2008

 

 

  • Level II test bed implementation

April 2009

 

 

  • Final project report

December 2009

 

 

Management Summary

% Program Schedule Elapsed:

27 % (as of Sept 07)

% Program Budget Expended:

11 % (as of Sept 07 )

Issues

 

This program summary includes:

    • CAMP (prime)
    • Volpe (Independent evaluator)