Research Archive

Description of Lines 25 to 53

Tasks 25 to 53 of the 2003 to 2007 Work Plan of the Electronic Freight Manifest

The graphic represents tasks on lines 25 to 53 of the FY 2003 to FY 2007 Work Plan of the Electronic Freight Management.

Many tasks in the graphic are subtasks of other tasks. The tasks are listed in bullets below, in proper hierarchical order and with the associated costs, where included, and the time span for each task.

Coalition Building (continued)

  • IFTWG (continued)
    • Milestones (continued)
      • Plan and facilitate IFTWG meetings – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
      • Record and distribute draft minutes of – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
      • Maintain a dedicated IFTWG web site page – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
      • Distribute inter-meetings information – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
      • Coordinate DOT and IFTWG activities with – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
      • Support for Stakeholder Communications, Outreach, and Coordination – IANNA Group, Q1 of FY 2005 to Q3 of FY 2007
  • EFM Steering Group – Q1 of FY 2003 to Q3 of FY 2007
    • Prepare SOW (Delcan) – Butler Group, $80K Cost in FY 2004, $80K Cost in FY 2005, $80K Cost in FY 2006, Q2, FY 2004 through Q4, FY 2004
    • Award Contract – Butler Group, FY 2004 through Q4, FY 2004
    • Milestones – Q3 of FY 2004 through Q3 of FY 2007
      • Program Management EFM Steering Group Support – Delcan Group, Q3 of FY 2004 through Q3 of FY 2007
      • Program Technical Support – Delcan Group, Q3 of FY 2004 through Q3 of FY 2007

EFM Foundation Elements – Q3 of FY 2003 through Q1 of FY 2006

  • EFM Standards –- Q3 of FY 2003 through Q1 of FY 2006
    • Prepare SOW (Mitretek) – Onder/Jones Groups, $220K Costs in FY 2004, $220K Costs in FY 2005, $220K Costs in FY 2006, Q2 of FY 2004 through Q1 of FY 2006
    • Prepare SOW (BAH) – Onder/Jones Groups, Q2 of FY 2004 through Q1 of FY 2006
    • Award Contracts – Q2 of FY 2004 through Q1 of FY 2006
    • Milestones – Q4 of FY 2003 through Q4 of FY 2005
      • Prep and Background Work – Q1 and Q2 of FY 2004
        • Assimilate '02 use case work – Onder/Jones Groups, Q2 of FY 2004
        • Understand latest UMM – Onder/Jones Groups, Q2 of FY 2004
        • Information collection in NY site visit – Onder/Jones Groups, Q1 of FY 2004
        • Collect documentation from TBG1&14 – Onder/Jones Groups, Q2 of FY 2004
        • Assimilate ESCM Phase III work – Onder/Jones Groups, Q2 of FY 2004
      • Use Case Development – Q4 of FY 2003 through Q1 of FY 2004
        • Create draft of UC documentation – Onder/Jones Groups, Q4 of FY 2003 to Q1 of FY 2004
        • Review w/functional experts: Air – Onder/Jones Groups, Q1 of FY 2004
        • Review w/functional experts: Truck – Onder/Jones Groups, Q1 of FY 2004
        • Review w/functional experts: Customs – Onder/Jones Groups, Q1 of FY 2004