Research Archive

Description of Lines 54 to 83

Tasks 54 to 83 of the 2003 to 2007 Work Plan of the Electronic Freight Manifest

The graphic represents tasks on lines 54 to 83 of the FY 2003 to FY 2007 Work Plan of the Electronic Freight Management.

Many tasks in the graphic are subtasks of other tasks. The tasks are listed in bullets below, in proper hierarchical order and with the associated costs, where included, and the time span for each task.

EFM Foundation Elements (continued)

  • EFM Standards (continued)
    • Milestones (continued)
      • Use Case Development (continued)
        • Update to second draft – Onder/Jones Groups, Q1 of FY 2004
        • Solicit feedback from Expert working group – Onder/Jones Groups, Q1 of FY 2004
        • Finalize use case documentation for WD – Onder/Jones Groups, Q1 of FY 2004
      • Activity Diagram Development – Q2 of FY 2004
        • Develop Activity diagrams – Onder/Jones Groups, Q2 of FY 2004
      • Data Element Development – Q3 of FY 2003 to Q2 of FY 2004
        • Create initial list, driven by ESCM – Onder/Jones Groups, Q4 of FY 2003
        • Conduct data element analysis – Onder/Jones Groups, Q1 to Q2 of FY 2004
        • Update list based on UC documentation – Onder/Jones Groups, Q2 of FY 2004
        • Update list based on UC second draft – Onder/Jones Groups, Q2 of FY 2004
        • Create data frames and messages – Onder/Jones Groups, Q2 of FY 2004
      • Write the Standard – Q1 to Q2 of FY 2004
        • Adapt CONOPS v.4.b – Onder/Jones Groups, Q1 of FY 2004
        • Draft Use case and activity diagrams – Onder/Jones Groups, Q1 of FY 2004
        • Draft Data elements, frames, messages – Onder/Jones Groups, Q1 of FY 2004
        • Create ASN.1 syntax – Onder/Jones Groups, Q2 of FY 2004
        • Draft foreword, scope, references – Onder/Jones Groups, Q1 of FY 2004
        • Draft Terms and definitions, acronyms – Onder/Jones Groups, Q1 of FY 2004
      • Finalize Working Draft (WD) Standard – Q2 of FY 2004
        • Review document editorially – Onder/Jones Groups, Q2 of FY 2004
        • Expert work group review – Onder/Jones Groups, Q2 of FY 2004
        • Final production – Onder/Jones Groups, Q2 of FY 2004
        • Submit to secretariat as WD – Onder/Jones Groups, Q2 of FY 2004
      • Harmonization – Q1 of FY 2004 through Q3 of FY 2004
        • CEFACT: send preliminary to Dominique – Onder/Jones Groups, Q1 of FY 2004
        • CEFACT: prepare for Bonn meeting – Onder/Jones Groups, Q1 of FY 2004
        • CEFACT: meet with TBG3 – Onder/Jones Groups, Q3 of FY 2004
        • CEFACT: assemble action list from – Onder/Jones Groups, Q3 of FY 2004
        • Harmonize with Cargo IMP – Onder/Jones Groups, Q2 of FY 2004 to Q3 of FY 2004
        • Harmonize with CCTS as needed – Onder/Jones Groups, Q2 of FY 2004 to Q3 of FY 2004