Tasks 84 to 107 of the 2003 to 2007 Work Plan of the Electronic Freight Manifest

The graphic represents tasks on lines 84 to 107 of the FY 2003 to FY 2007 Work Plan of the Electronic Freight Management.

Many tasks in the graphic are subtasks of other tasks. The tasks are listed in bullets below, in proper hierarchical order and with the associated costs, where included, and the time span for each task.

EFM Foundation Elements (continued)

  • EFM Standards (continued)
    • Milestones (continued)
      • Usher Standard through Committee Process – Q2 of FY 2004 to Q4 of FY 2005
        • Solicit review and comment from Working Group – Onder/Jones Groups, Q2 of FY 2004
        • Present CD to ISO TC204 for review and comment – Onder/Jones Groups, Q3 of FY 2004
        • Present CD to ISO TC204 for ballot – Onder/Jones Groups, Q3 of FY 2004
        • Hold CD comment resolution meeting – Onder/Jones Groups, Q4 of FY 2005
        • Circulate resolution for DIS ballot – Onder/Jones Groups, Q4 of FY 2005
        • Ensure Central Secretariat issues DIS ballot – Onder/Jones Groups, Q1 of FY 2005
        • DIS adoption – Onder/Jones Groups, Q2 of FY 2005
  • Monitor and Adopt Biometric Standard – Q2 of FY 2004 to Q2 of FY 2005
    • Prepare SOW (Mitretek Support) – Butler Group, $30K Cost in FY 2004, $30K Cost in FY 2005, $30K Cost in FY 2006, Q2 of FY 2004
    • Award Contract – Butler Group, Q3 of FY 2004
    • Milestones (Biometric Standard) – Q3 of FY 2004 through Q1 of FY 2005
      • Biometrics reviews and briefings – Butler Group, Q3 of FY 2004 through Q1 of FY 2005
      • Preliminary technical and operational risk & threat assessment – Butler Group, Q3 of FY 2004 through Q1 of FY 2005
      • Integrated risk and threat assessment – Butler Group, Q3 of FY 2004 through Q1 of FY 2005
  • Monitor and Adopt E-Seal Device Standard – $30K Cost in FY 2004, $30K Cost in FY 2005, $30K Cost in FY 2006, Q3 of FY 2004 through Q4 of FY 2005
    • Prepare SOW (Mike Wolfe) – Onder Group, Q3 of FY 2004
    • Award Contract – Onder Group, Q3 of FY 2004
    • Milestones – Q3 of FY 2004 through Q4 of FY 2005
      • Ongoing support with technical committees developing standards – Wolfe Group, $30K Cost in FY 2004, $30K Cost in FY 2005, $30K Cost in FY 2006, Q3 of FY 2004 through Q4 of FY 2005
  • EFM Information Highway – Q1 of FY 2004 to Q3 of FY 2005
    • Develop Operational Plan and Tools – Q1 of FY 2004 to Q3 of FY 2005
      • Prepare SOW (ATRI) – Butler Group, $225K Cost in FY 2004, Q1 of FY 2004
      • Award Contract – Butler Group, Q3 of FY 2004