Description of Timeline

Four-year timeline toward building and replicating a Traveler Management Coordination Center

The figure illustrates a four-year timeline toward building and replicating a Traveler Management Coordination Center.

The time span starts at the beginning of 2004 and ends at the beginning of 2008.

From 2004 through mid-2005, there will be Development of a Systematic Approach for Selecting Demonstration Sites as well as an Assessment of Technologies that Improve Accessibility.

From the end of 2004 to near the end of 2006, there will be a Conduction of field tests to determine the return on investment of various ITS applications that improve accessibility and human services transportation coordination.

From mid-2006 through mid-2007, there is Development of the "Traveler Management Coordination Center."

By the end of 2008, there should be a replicable "Traveler Management Coordination Center."


1200 New Jersey Avenue, SE • Washington, DC 20590 • 800.853.1351 • E-mail OST-R

Accessibility | Disclaimer | Fast Lane | FedStats | Freedom of Information Act | No FEAR Act | OIG Hotline | Privacy Policy | USA.gov | White House


OST-R's privacy policies and procedures do not necessarily apply to external web sites. We suggest contacting these sites directly for information on their data collection and distribution policies.